FAQ: Concrete Costs Per Yard 2016?

How much does 4 yards of concrete cost?

Each cubic yard of concrete costs $119 to $147 per cubic yard delivered. Short-Load Concrete Prices.

Cubic Yards Mixing On-site Fees
4 – 4.75 $80
3 – 3.75 $90
2 – 2.75 $100
1 – 1.75 $110

How much does it cost to concrete a backyard?

The typical concrete patio is approximately 288 sq ft and costs an average of $2,800 (about $9 per sq ft); depending on a variety of factors, your cost will likely fall between $1,300 and $5,100 ($3-$15 per sq ft).

How much does concrete run per yard?

How much is concrete? Concrete costs from $113 to $126 per cubic yard or between $2.83 to $3.57 per square foot depending on the thickness of the slab poured.

How much does 3 cubic yards of concrete cost?

Concrete is typically priced by the cubic yard, with additional fees for delivery. The average homeowner paving a 10 x 20-foot driveway will need approximately 3 cubic yards of concrete at a cost of approximately $410.

You might be interested:  Question: How To Attach 4x4 To Concrete?

How many bags of concrete do I need for a 10×20 slab?

A 60-pound bag yields. 017 cubic yards, and an 80-pound bag yields. 022 cubic yards. For a 10 x 10 slab, you would need 77 60-pound bags or 60 80-pound bags.

Can I pour a 2 inch concrete slab?

If done properly, new concrete can often be poured right over an existing slab. For this to be feasible, the contractor needs to pour at least 2 inches thick, use smaller aggregate, and incorporate reinforcement such as welded wire mesh or fiber mixed into the concrete.

Can you pour concrete directly on dirt?

Long story short, yes you can pour concrete over dirt.

How much does a 20×20 stamped concrete patio cost?

The average cost for a stamped concrete is $5 to $12 per square foot, not including the concrete slab which costs $2 – $7 per square foot. Most homeowners spend a total of between $3,751 – $8,540 for stamped concrete patio. Get free estimates from concrete pros near you.

How much does a 20×20 patio cost?

Cost to Put in a New Patio by Size

7×7 $250-$2,500
10×10 $500-$5,000
12×12 $750-$7,200
16×18 $1,450-$14,500
20×20 $2,000-$20,000

How many 80lb bags of concrete make a yard?

how many 80lb bags of concrete are in a yard? You will need 45 bags of concrete mix to make a cubic yard of concrete. There’s 27 cubic feet of concrete in a cubic yard.

Is it cheaper to mix your own concrete?

One of the least expensive ways to get concrete is to mix your own. You can buy bags of the mix from a home improvement store. Typically, you only have to add water for it to be ready to pour. Otherwise, you risk getting a weaker concrete once it cures, which could lead to cracks or crumbles within a couple of years.

You might be interested:  Readers ask: How To Calculate Concrete Stairs?

How much concrete can one person pour in a day?

It all depends on how and where you are pouring the concrete and how you are finishing it. When we were placing concrete for a parking lot we poured 1000 cubic yards a day or about 10 cubic yards in 5 min. When we were placing concrete for a bridge deck 200 cubic yards took all day or about 10 cubic in 25 min.

Do you need rebar for 4 inch slab?

No, you do not need rebar for a 4 – inch slab of concrete on grade. A 4 – inch -thick slab cast on the ground and in permanent contact with it will float and rebar is not required. Rebar is recommended on concrete measuring 5 – 6 inches thick.

How much does 20 yards of concrete cost?

Use $90 per cubic yard as a ballpark figure for concrete prices, but concrete slab cost will vary by region. Also, expect a fee of about $60 per load for delivery from a concrete truck for concrete cost. There could be other fees for such things as Saturday concrete truck delivery and small loads.

How thick should the concrete be for a driveway?

As for thickness, non-reinforced pavement four inches thick is standard for passenger car driveways. For heavier vehicles, a thickness of five inches is recommended. To eliminate standing water, the driveway should be sloped towards the street a minimum of one percent, or 1/8 inch per foot, for proper drainage.